1. Remove the protective covers on both sides of the flange end, and wash and clean when the valve is fully opened.

2. Before installation, the whole machine shall be tested according to the specified signal (electric or pneumatic) (to prevent vibration caused by transportation from affecting the service performance), and can only be installed online after passing the test (wiring shall be in accordance with the circuit diagram of electric actuator).

3. Before connecting with the pipe, wash and remove the remaining impurities in the pipe (these substances may damage the valve seat and ball).

4. During installation, please do not use the actuator of the valve as the lifting point to avoid damaging the actuator and accessories.

5. This type of valve shall be installed in the horizontal or vertical direction of the pipeline.

6. The pipeline near the installation point shall not sag or bear external forces, and the pipeline support or support can be used to eliminate the deviation of the pipeline.

7. After connecting with the pipe, please cross lock the flange connecting bolts with the specified torque.